North Shore 1 Contract 10-047-3S
Project Overview
The Village’s of Winnetka, Kenilworth, Wilmette and Evanston local sewer system flows into a series of large diameter pipes owned and maintained by the Metropolitan Water Reclamation District (MWRD). These pipes, known as interceptor sewers, convey regional flows to an MWRD treatment plant. An inspection of the North Shore 1 intercepting sewer by the MWRD showed the presence of sewage solids deposits, root intrusions, infiltration, offset joints, broken connections, and concrete erosion. The sewer was constructed back in 1913 and has been in constant service since it went online. In order to restore the hydraulic and structural integrity of this aging sewer, it needs to be rehabilitated. In addition, physical inspections of the manholes revealed cracks and holes in the walls and bases of the manholes. As with the main sewer line, in order to restore the structural integrity of these structures, the manholes need to be rehabilitated as well. The overall project will consist of multiple phases, with a total project duration of up to 3 years to complete the work in all communities.
Current Conditions
Coming Soon!
Future Improvements
The rehabilitation of 14,400+ linear feet of sewer lines and Manholes from Winnetka to Wilmette Illinois. Plus additional New Manholes to be installed in Evanston Illinois.
Project Work Overview
Sewer Relining and Manhole Rehabilitation on Sheridan Rd. from Cherry Rd. Winnetka, IL to Sheridan Rd. Bridge or approximately 613 Sheridan Rd., Wilmette, IL. (Roughly 2.5 miles.)
Three individual manhole locations for new manholes to be installed at:
703 Sheridan Rd., Evanston, IL | 525 Sheridan Square., Evanston, IL | 7799 N. Sheridan Rd. Evanston, IL
Type of Work Performed
Sewer manhole inspections by man entry, sewer televising and maintenance repairs. 23 total manhole locations need to be accessed. Installation/Excavation of 7 Shaft locations for installing new sewer pipe for rehabilitation via Slip lining Method which is a trenchless technology.
Duration
This is a 1,000 Calendar Day project, approximately 3 years.
Schedule/Phasing
The work will be performed in phases starting from the North and working South. To install the sewer pipe via slip lining, we need an insertion shaft and a receiving shaft. We will not be opening more than 2 shafts for extended periods of time. Typically, two shafts will be open for 3-4 months as we install the new sewer pipe in between the two shafts. There may be a short time when there is a third shaft open when we plan to move between work areas.
Work Time
7AM to 5PM daily work duration with option to work Saturdays if possible.
The actual work will be only accessing one manhole at a time for 1-2 hours for an initial inspection of approximately 23 manholes. Following the inspection, we will return to approximately 8 of the manholes for televising via robotic and man entry. The televising will be 3-4 hours. If the weather allows, we could realistically complete all the maintenance work in 1 week, but it could take up to 1 month.
Phasing & Traffic Control Overview
The MWRD has provided an extensive traffic control plan for the entirety of the project.
Phase I Cleaning/Televising: We will set up daily temporary lane closure for intermittent operations. Most of the inspection locations we will only need to close the lane during work hours.
*What to Expect – Traffic Delays with lane re-direction on Northbound Sheridan Rd. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 2-3 months for Cleaning and 30 days for Televising.
Phase II Access Pit/Shaft Installations: Access Pit/Shaft will be open for 3-4 months, with permanent lane closures in place as the work is performed daily within these shafts. Which will typically be only two shafts at a time.
*What to Expect – Traffic Delays with lane re-direction on Northbound Sheridan Rd. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 3-4 months.
Phase III Access Pit/Shaft Restorations: the access pit/shaft excavations will be restored per IDOT standards.
*What to Expect – Traffic Delays with lane re-direction on Northbound Sheridan Rd. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 30 days.
Phase IV Manhole Rehabilitation: This will be a small daily lane closure needed for access to all 26 manholes to rehabilitate them.
*What to Expect – Traffic Delays with lane re-direction on Northbound Sheridan Rd. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 1-2 months.
Phase V New Manhole Installation (Evanston Only): Access Pit/Shaft will be open for 1-2 months, with permanent lane closures in place as the work is performed daily within these shafts. Which will typically be only two shafts at a time. Access Pit/Shaft will be restored per IDOT standards.
*What to Expect – Traffic Delays with lane re-direction on Northbound Sheridan Rd. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 1-2 months.
Phase TBD: Sewer Bypass Setup: Transformers to be installed at two locations (Cherry Rd. & Winnetka Ave) to provide continuous power to our bypass pumps.
*What to Expect – Minor sidewalk interruptions for Transformers to be installed along the easement of Sheridan Rd. at the Intersections of Cherry Rd. and Winnetka Ave. during the hours of 7AM to 5PM Monday thru Friday, (Saturday work determined by necessity) duration is anticipated to take 1-2 weeks.
Frequently Asked Questions
Will my utilities (i.e. Water, Sewer or Electric) be affected?
No there will not be any limiting of Water, Sewer or Electric usage.
Will there be traffic impacts?
Occasionally on Northbound Sheridan Road there will be temporary daytime lane closures, additionally at certain phases of the project there will be permanent lane closures for a period of up to 3 months.
How long will this project take?
The scheduled duration of the project is 1,000 calendar days or 3 years.
What contractors can you expect to see on our job site?
Airy’s Inc. (Excavation) – AMS Elite Solutions, LLC (Trucking)- MCSP (Manhole Rehab) – MixOnSite USA, Inc. (Annular Grouting) – Sheridan Plumbing & Sewer, Inc. (Cleaning & Televising) – Work Zone Safety, Inc. (Traffic Control) – Nadar (Drone Survey)
What is the purpose of this project?
To rehabilitate 14,000 feet of 90 inch, 100-year-old combination (sanitary and storm) sewer lines as preventative maintenance.
Inliner Solutions, a PURIS Company, has over 25 years experience in the rehabilitation industry and has grown through a series of mergers and acquisitions to become one of the largest privately held wastewater infrastructure renewal construction companies in North America. As an established leader in the infrastructure renewal industry with 18 offices and more than 650 employees, Inliner has the financial strength, industry expertise, staff leadership, and technical capabilities to meet nationwide demand.